Unit 8 - Reinstatement of concrete slabs

The unit 8 module deals with reinstatement of concrete slabs on the public highway and covers the legal and practical aspects of undertaking this work. The unit is available for operatives only.

  • Select and use the appropriate personal protective equipment correctly.
  • Prepare the cavity to recieve the reinstatement
  • Make good the sub-base layer. Mark out and drill for dowel bars to the correct depth and positioning
  • Cut dowel bars and mesh reinforcing to correct length and size
  • Use a pavement saw the ensure the correct edge is achieved. Rough cut the remaining depth to expose reinforcing in accordance with the specifications.
  • Position dowel bars and tie reinforcing securely
  • Place slip membrane correctly
  • Replace any missing or damaged joints in the slab to match existing
  • Slump test concrete to ensure workability
  • Place and compact concrete to the required level
  • Ensure that skid resistance is achieved
  • Use approved curing procedures
  • Dispose of surplus material safely
  • Follow safe working practices, including the selection and use of personal protective equipment and use of plant equipment
  • Provide sufficient knowledge evidence by way of oral or written questions

On completion of this unit delegates recieve a CAWBI certificate and this unit can then be put towards a full streetworks qualification when combined with other units.

 